sr 60 emergency repairs (hurricane charley)

  • 1
  • 2
  • 3
  • 4
  • 5

 

During Hurricane Charley in 2005, SR 60 sustained significant damage to the eastbound lanes due to erosion of the shoulder and undermining of the pavement along a stretch of this main roadway east of Lake Wales, Florida. The repair entailed driving two permanent rows of steel sheet piling, separated by 20’ buffer, for a distance of 1,220’ where the shoulder had been eroded. The void between the rows of sheeting was filled with flowable fill and capped with concrete, creating a new stable shoulder which enabled the reconstruction of the damaged highway.

Project Details

  • Location:
    Polk County, FL
  • Completed:
    2005
  • Client:
    FDOT